COMMERCIAL DISPUTES  ·  COMMERCIAL

8 days late, but Supreme Court says: condone it

HUDA filed objections to an arbitration award eight days after the deadline. The lower courts threw it out. The Supreme Court just sent it back for a fresh hearing.

8

days.

Condoned. Eight days late.
TL;DR

HUDA filed objections to an arbitration award eight days after the deadline. The lower courts threw it out. The Supreme Court just sent it back for a fresh hearing.

In this reading
1. The park that refused to stay finished 2. The eight days that almost cost HUDA everything 3. When the Supreme Court saw what the lower courts missed 4. "Cryptic and perfunctory reasoning is insufficient" 5. The order: condoned, set aside, sent back 6. What this means for every commercial dispute

HUDA missed the deadline to challenge a ₹1.2 crore arbitration award by just 8 days. The trial court said: too late. The Supreme Court said: not so fast.

On a March afternoon in 2022, a two-judge bench of the Supreme Court — Justice Ajay Rastogi and Justice Sanjiv Khanna — looked at a file that had been moving through courts for nearly a decade. At its centre was a simple question: could a government agency lose its right to challenge a massive arbitration award simply because its lawyers took eight extra days to file the paperwork? The answer, the bench decided, was no.

The park that refused to stay finished

In 1998, the Haryana Urban Development Authority (HUDA) hired Mehta Construction Company to build water features, bridges, and related structures for a town park in Karnal. The contract was worth about ₹32.50 lakhs, later revised to ₹45.87 lakhs. The work was completed in August 1999.

Then the trouble began.

HUDA claimed the contractor had failed to finish on time. The contractor blamed HUDA for the delays — saying the authority hadn't provided the necessary clearances or site access. For over a decade, the dispute simmered. Neither side moved to resolve it formally.

In 2012, the contractor finally filed an application under Section 11(6) of the Arbitration and Conciliation Act (the provision that allows a party to ask the High Court to appoint an arbitrator when the other side refuses to cooperate). The Punjab and Haryana High Court disposed of the application by directing the parties to approach an arbitrator.

The sole arbitrator — a Superintending Engineer from HUDA's own circle in Karnal — heard the matter and, in December 2013, delivered an award that stunned the authority: ₹1,19,69,945 with 18% interest. Nearly ₹1.2 crores, plus interest that would keep compounding.

The eight days that almost cost HUDA everything

HUDA needed to challenge the award. Under Section 34 of the Arbitration Act (the provision that allows a party to ask a court to set aside an arbitral award), a challenge must be filed within three months from the date of receiving the award. Section 34(3) gives a further thirty-day window — a condonable period — if the party can show sufficient cause for the delay.

HUDA filed its objections eight days beyond the three-month deadline. Along with the objections, it filed a condonation application (a formal request asking the court to excuse the delay). The explanation was straightforward: the authority needed time to engage counsel, examine the voluminous records, and obtain the necessary sanctions from senior officials.

The Additional District Judge in Karnal was not impressed. In January 2018, the judge dismissed HUDA's objections on two grounds: first, that the delay was not sufficiently explained, and second — more troublingly — that the objections lacked merit. The judge did not examine the specific grounds HUDA had raised. The order was, in the Supreme Court's later words, "cryptic and perfunctory."

HUDA appealed to the Punjab and Haryana High Court under Section 37 of the Arbitration Act (the provision that allows appeals against orders under Section 34). A single judge dismissed the appeal in December 2019, essentially endorsing the trial court's reasoning without a fresh examination.

When the Supreme Court saw what the lower courts missed

By the time the matter reached the Supreme Court in March 2022, HUDA had been fighting for nearly a decade over a project that had been completed in 1999. The bench looked at the timeline and saw something the lower courts had missed.

The proviso to Section 34(3) of the Arbitration Act clearly allows a court to condone a delay of up to thirty days beyond the three-month limitation period, provided the applicant shows sufficient cause. Eight days fell comfortably within that window. The question was whether HUDA's explanation — that it needed time to engage counsel, examine records, and obtain sanctions — constituted sufficient cause.

The Supreme Court held that it did. Government agencies, the bench observed, operate through a chain of decision-making. They cannot file objections the way a private individual might. The need to consult records, obtain legal opinions, and secure approvals from competent authorities is a genuine procedural reality, not a manufactured excuse.

But the court did not stop there. It went on to examine how the lower courts had handled the substantive objections — and found the reasoning deeply inadequate.

"Cryptic and perfunctory reasoning is insufficient"

The Supreme Court noted that the Additional District Judge had dismissed HUDA's objections "in a cursory manner" without properly examining the issues raised. The judge had not dealt with the specific grounds under Section 34(2A) of the Arbitration Act (the provision that allows a court to set aside an award if it is vitiated by "patent illegality appearing on the face of the award"). Nor had the judge examined the question of limitation under Section 43 of the Act (the provision that applies the Limitation Act to arbitration proceedings).

The High Court, in turn, had simply affirmed the trial court's order without conducting its own independent analysis. The result was a double failure: neither court had given the objections the scrutiny they deserved.

"Cryptic and perfunctory reasoning that does not deal with specific issues and contentions is insufficient," the Supreme Court held. The lower courts had, in effect, short-circuited the statutory process designed to ensure that arbitration awards are properly tested before they become final.

The order: condoned, set aside, sent back

The Supreme Court allowed HUDA's appeal. It set aside both the High Court's order of December 2019 and the Additional District Judge's order of January 2018. The matter was remitted back to the Additional District Judge in Karnal for a fresh hearing on merits.

The bench made it clear that its observations were not binding on the trial court. The judge would hear the objections afresh, consider the grounds raised, and decide the matter on its own merits. No costs were imposed on either party.

The operative order was clean and precise: the eight-day delay was condoned, the cryptic orders were set aside, and the case was sent back for a proper hearing.

THE PLAY: When filing objections under Section 34 of the Arbitration Act, always file a condonation application alongside if you are even one day late — and ensure the trial court's order explicitly addresses each ground of challenge, so a cryptic dismissal does not become the final word.

What this means for every commercial dispute

For practitioners, the message is twofold. First, the thirty-day condonable window under Section 34(3) is not a formality — courts must actually consider whether the delay is explained, not mechanically reject it. Second, and more importantly, courts dealing with arbitration objections must provide reasoned orders that engage with the specific issues raised. A one-paragraph dismissal that says "no merit" is no longer acceptable.

For parties — especially government agencies and public sector undertakings — the judgment offers a practical lifeline. The procedural reality of bureaucratic decision-making is now judicially recognised as a valid ground for a short delay. But the window remains narrow: thirty days, no more, and the explanation must be genuine.

The case also serves as a reminder that arbitration does not end with the award. The challenge under Section 34 is a substantive right, and courts must exercise it with the same care they would apply to any other judicial proceeding. Cryptic orders, the Supreme Court has now made clear, will not survive scrutiny.

The park in Karnal was completed in 1999. The legal battle over who paid for it is still not over. But at least now, it will be heard properly.

§    §    §

Reviewed by Sharad Bansal on 15 · 05 · 2026

Sharad Bansal — Sharad Bansal is an advocate of the Delhi High Court with twenty years of practice in criminal defence and commercial litigation.

SUBSCRIBE

A weekly reading by post.

One short email each week — the most useful judgment of the week, distilled for advocates, CFOs, and founders. Free. Unsubscribe in one click.

By subscribing you agree to our Privacy & Disclaimers.