A power company won ₹26 crore in arbitration. The state tried to kill the award. Here's what the Supreme Court did.
The state said the contract was terminated because the company didn't get clearances in time. The company said: you pulled the plug too early. The arbitrator agreed — but then the High Court wiped out the entire award.
26
crores.
The state said the contract was terminated because the company didn't get clearances in time. The company said: you pulled the plug too early. The arbitrator agreed — but then the High Court wiped out the entire award.
A hydroelectric project. A terminated deal. An arbitrator said the state jumped the gun. Then the High Court erased the ₹26 crore award entirely.
The dispute arose when the State of Himachal Pradesh terminated the agreement before the prescribed period expired. UHL Power Company claimed the termination was premature — the required clearances, techno-economic and environmental, had not been obtained, and the timeline should have been extended. The state took the opposite view.
For years, two questions hung over the UHL-III Hydro-electric Project in the hills of Himachal Pradesh. Could a state government tear up a power agreement before the deadline for obtaining clearances had expired? And if an arbitrator said the termination was wrong, could a court simply throw out the entire compensation award?
1992. A deal. A deadline. A termination.
In 1992, UHL Power Company entered into a Memorandum of Understanding (MoU) with the State of Himachal Pradesh to build the UHL-III Hydro-electric Project — a 100 MW power plant in the hills. Five years later, in 1997, the two sides formalised their arrangement with an Implementation Agreement. The MoU was expressly referred to as an Appendix in the Implementation Agreement, and the definition clause of the latter included all appendices and annexures.
The company needed two critical approvals before construction could begin: a techno-economic clearance and an environmental clearance. Neither came quickly. The stack of clearance applications grew thick on government desks, but the approvals did not arrive. The project sat in limbo.
Then the state moved. Before the period prescribed in the agreement had run out, the Himachal Pradesh government terminated the deal. UHL Power Company said the termination was premature — the clearances hadn't been obtained, but the timeline should have been extended. The state said the company had failed to perform.
The arbitrator said: ₹26 crore
The dispute went to a Sole Arbitrator. On 5 June 2005, after hearing both sides, the arbitrator ruled in favour of UHL Power Company. The termination, the arbitrator found, was premature. The company was entitled to compensation: ₹26,08,89,107.35 — about ₹26 crore — including compound interest.
The state refused to accept the award. It filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996 (the provision that allows a court to set aside an arbitral award on limited grounds). On 16 December 2008, the Single Judge of the Himachal Pradesh High Court agreed with the state — and wiped out the entire award. The order sheet of the Single Judge recorded the complete disallowance of UHL's claim.
UHL Power Company appealed under Section 37 of the same Act (which allows a party to challenge a Section 34 order before a Division Bench). On 24 May 2011, the Division Bench partly restored the award. It agreed that the termination was wrongful and that UHL deserved compensation. But it changed one crucial thing: it replaced the compound interest awarded by the arbitrator with simple interest at 6% per annum, relying on the Supreme Court precedent State of Haryana v. S.L. Arora and Co. (2010).
Why the interest rate became the battleground
Both sides were unhappy. UHL Power Company wanted its compound interest back. The state wanted the entire award killed. Both appealed to the Supreme Court — UHL in Civil Appeal No. 10341 of 2011, and the State in Civil Appeal No. 10342 of 2011.
The state's appeal faced an immediate problem. The Supreme Court has repeatedly held that the jurisdiction under Section 34 is narrow, and under Section 37 it is even narrower. As the court stated in its judgment, "courts exercising jurisdiction under Sections 34/37 cannot act as appellate courts over arbitral awards." They cannot re-examine the evidence or substitute their own view of the contract for the arbitrator's view — as long as the arbitrator's interpretation was a plausible one.
The Division Bench had already found that the state's termination was premature. The Supreme Court, a bench of three judges — Justice N.V. Ramana, Justice A.S. Bopanna, and Justice Hima Kohli — saw no reason to disturb that finding. The court upheld the Appellate Court's findings on the merger of the MoU with the Implementation Agreement and on the premature termination by the State. The state's appeal was dismissed entirely.
That left the question of compound interest. The Division Bench had relied on S.L. Arora, which had held that an arbitrator could not award compound interest on the interest component of the award. But by the time the case reached the Supreme Court in January 2022, S.L. Arora had been overruled by a three-judge bench in Hyder Consulting (UK) Ltd. v. Governor, State of Orissa through Chief Engineer (2015).
The Supreme Court said: compound interest stands
The key question under Section 31(7) of the Arbitration Act (which deals with interest on the arbitral award) was this: when the law says an arbitrator can award interest on "the sum directed to be paid by the arbitral award", does that sum include both the principal amount and the interest component?
The Supreme Court said yes. The phrase "sum directed to be paid" covers the entire amount the arbitrator has ordered — principal plus accrued interest. An arbitrator can therefore award post-award interest on the total amount, including the interest component. S.L. Arora, which had held otherwise, was no longer good law after Hyder Consulting.
The court restored the compound interest awarded by the Sole Arbitrator. UHL Power Company's appeal was partly allowed on that point.
The MoU that became an appendix
The state had raised another argument: the arbitration clause in the Implementation Agreement didn't cover disputes arising from the earlier MoU. The Supreme Court rejected this. The MoU was expressly referred to as an Appendix in the Implementation Agreement. The definition clause of the Implementation Agreement included all appendices and annexures. The MoU had merged into the Implementation Agreement. Disputes under the MoU were therefore covered by the arbitration clause in the later agreement.
The court applied a settled principle: where a Memorandum of Understanding is expressly referred to as an Appendix in a subsequent Implementation Agreement, and the definition clause of the latter includes all appendices and annexures, the MoU merges into the Implementation Agreement, and disputes thereunder are referable to arbitration under the latter's arbitration clause.
The Supreme Court also cited several precedents in support of its reasoning on the narrow scope of Section 34/37 review, including MMTC Limited v. Vedanta Limited (2019), K. Sugumar v. Hindustan Petroleum Corporation Ltd. (2020), Dyna Technologies (P) Ltd. v. Crompton Greaves Ltd. (2019), Parsa Kente Collieries Limited v. Rajasthan Rajya Vidyut Utpadan Nigam Limited (2019), South East Asia Marine Engg. & Constructions Ltd. v. Oil India Ltd. (2020), and McDermott International Inc. v. Burn Standard Co. Ltd. (2006).
THE PLAY: When drafting arbitration clauses, specify explicitly whether the arbitrator can award compound interest on both principal and accrued interest — but know that after Hyder Consulting, the default position under Section 31(7) already allows it.
The state's appeal was rejected in full. UHL Power Company got its compound interest back. The project itself was long dead — but the law on who pays for a wrongful termination, and at what rate, was settled.
The Supreme Court ordered that Civil Appeal No. 10341 of 2011 preferred by UHL was partly allowed to the extent mentioned in para 6 of the judgment, and Civil Appeal No. 10342 of 2011 filed by the State of Himachal Pradesh was rejected in toto. The parties were left to bear their own costs.