COMMERCIAL DISPUTES  ·  COMMERCIAL

NDMC loses arbitration battle as SC clarifies IBC moratorium period exclusion

The Supreme Court held that the entire moratorium period under IBC must be excluded from limitation computation even for suits filed by the corporate debtor, not just against it.

18

months.

Excluded. Moratorium period
TL;DR

The Supreme Court held that the entire moratorium period under IBC must be excluded from limitation computation even for suits filed by the corporate debtor, not just against it.

In this reading
1. The contract that soured 2. When insolvency froze everything 3. The arbitration application — and the limitation objection 4. The core legal question 5. What the Supreme Court held 6. The judgment's own words 7. Why this matters for commercial contracts

NDMC terminated a Rs.16.2 crore contract. Minosha waited 4 years to seek arbitration. The Supreme Court said: the clock stopped during insolvency.

When a company enters insolvency, the law freezes all legal proceedings against it. But what happens to the company's own right to file a case? Can it count the insolvency period as time that does not eat into the limitation clock — the legally fixed deadline to approach a court? The Supreme Court faced this exact question in a dispute between New Delhi Municipal Council (NDMC) and Minosha India Limited. Its answer reshaped how limitation interacts with the Insolvency and Bankruptcy Code (IBC).

The contract that soured

In February 2015, NDMC placed a Rs.16.2 crore purchase order with Minosha India Ltd. The purchase order letter — a single sheet carrying the weight of a business partnership — was signed and exchanged. The business relationship collapsed quickly. NDMC terminated the contract, citing non-responsiveness from Minosha. Minosha challenged the termination before the Delhi High Court, which directed NDMC to hear Minosha's side of the story. NDMC heard Minosha's representation — and rejected it on 17 May 2016.

Minosha did not let the matter rest. In June 2016, it invoked the arbitration clause in the contract. NDMC responded on 20 July 2016, but instead of agreeing to Minosha's nominees, it suggested the Delhi International Arbitration Centre (DIAC) as the forum. The parties were at a standoff. Then something else intervened.

When insolvency froze everything

In May 2018, the National Company Law Tribunal (NCLT) in Mumbai admitted an insolvency application filed by Minosha itself under Section 10 of the IBC (a provision allowing a corporate debtor to initiate its own insolvency process). The NCLT order sheet, dated 14 May 2018, bore the stamp of the Mumbai bench. It declared a moratorium: a legal freeze that stops all legal proceedings, debt recovery actions, and asset transfers against the company. A resolution plan (a court-approved revival scheme) was approved on 28 November 2019. The resolution plan document, thick with schedules and creditor lists, marked the end of Minosha's suspended existence.

For nearly 18 months, Minosha existed in this suspended state. The company could not pursue its arbitration claim during this period because the moratorium under Section 14 of the IBC (the freeze on proceedings against the corporate debtor) was in force. But here is the twist: Section 14 bars proceedings against the company, not proceedings by the company. Minosha's arbitration claim was something it wanted to file against NDMC, not something NDMC wanted to file against it.

The arbitration application — and the limitation objection

In November 2020, more than four years after NDMC rejected Minosha's representation, Minosha filed an application under Section 11(6) of the Arbitration and Conciliation Act, 1996 (a provision that allows a party to ask the court to appoint an arbitrator when the other side refuses to cooperate). The Delhi High Court appointed an arbitrator by consent of both parties on 14 December 2020.

NDMC appealed to the Supreme Court. Its argument was straightforward: the limitation period to seek appointment of an arbitrator under the Arbitration Act is three years from when the right to seek arbitration arose. Minosha invoked arbitration in June 2016. NDMC replied in July 2016. By November 2020, more than four years had passed. The claim, NDMC said, was dead on arrival.

Minosha had a counter-argument. It pointed to Section 60(6) of the IBC, which says that the period during which a moratorium is in force must be excluded from the computation of limitation for any suit or application "by or against" the corporate debtor. The entire moratorium period — from May 2018 to November 2019 — should be carved out, Minosha argued. Once you remove those 18 months, the clock had not run out.

The clock stopped. That was the heart of the case.

The core legal question

The Supreme Court had to decide one issue: does Section 60(6) of the IBC allow exclusion of the moratorium period only for proceedings that are barred by the moratorium (i.e., proceedings against the corporate debtor), or does it also apply to proceedings initiated by the corporate debtor — which the moratorium does not bar?

NDMC's argument had a surface logic. The moratorium under Section 14 only freezes proceedings against the company. Minosha could have filed its arbitration application during the moratorium period because it was the claimant, not the defendant. Since the moratorium did not stop Minosha from acting, why should Minosha get the benefit of excluding that period from limitation?

Minosha's response was rooted in the plain language of Section 60(6). The provision says: "the period during which a moratorium is in force in respect of the corporate debtor shall be excluded in computing the period of limitation for any suit or application by or against the corporate debtor." The words "by or against" are unambiguous, Minosha said. The exclusion applies to both sides.

What the Supreme Court held

Justice K.M. Joseph and Justice Hrishikesh Roy, composing the bench, dismissed NDMC's appeal. The bench read out the operative order. The court held that the plain language of Section 60(6) unambiguously provides for exclusion in respect of suits or applications "by or against" the corporate debtor. The phrase "for which an order of moratorium has been made" in Section 60(6) serves as a reference point — it identifies which moratorium period to exclude — and not as a restrictive qualifier that limits the exclusion only to proceedings barred by the moratorium.

The court applied the principle of literal interpretation: when the words of a statute are clear, the court must give effect to them even if the result seems inconvenient. The bench cited its own precedent in Noharlal Verma v. District Cooperative Central Bank Limited and the classic statement in Reserve Bank of India v. Peerless General Finance & Investment Co. Ltd. that a statute must be read as a whole and given its plain meaning.

The court also noted that during the moratorium period, the management of the corporate debtor passes to the interim resolution professional (IRP) under Section 17 of the IBC (a provision that transfers control of the company to an independent professional during insolvency). The IRP's powers are limited by the resolution process. It would be impractical to expect the corporate debtor to pursue litigation during this period, even if the moratorium technically does not bar it from doing so.

The judgment's own words

The Supreme Court, in its reasoning, stated that the language of Section 60(6) "unambiguously provides for exclusion in respect of suits/applications 'by or against' the corporate debtor." The court further explained that the phrase "for which an order of moratorium has been made" serves as "a reference point and sine qua non, not as a restrictive qualifier limiting exclusion only to proceedings barred by moratorium." This direct statement from the bench cut through NDMC's argument and settled the law.

Why this matters for commercial contracts

This judgment settles a recurring ambiguity in insolvency law. Parties to commercial contracts often face a situation where the limitation period for their claim is running while the other side is undergoing insolvency. The natural instinct is to rush to court before the clock runs out. But this judgment confirms that the corporate debtor — the company undergoing insolvency — can safely wait until the resolution plan is approved, and the entire moratorium period will be excluded from limitation computation.

For counterparties like NDMC, the message is different. If you are dealing with a company that has entered insolvency, you cannot assume that its claims against you will die of old age. The moratorium period gives the corporate debtor a fresh lease on limitation time. The practical takeaway: preserve evidence and documents, because the claim may resurface years later.

THE PLAY: When computing limitation for any proceeding by or against a corporate debtor, exclude the entire period from the date the NCLT admits the insolvency application to the date the resolution plan is approved — regardless of whether the proceeding was actually barred by the moratorium.

The court ended where it began: with a contract, a termination, and a clock that stopped ticking the day insolvency began.

§    §    §

Reviewed by Sharad Bansal on 15 · 05 · 2026

Sharad Bansal — Sharad Bansal is an advocate of the Delhi High Court with twenty years of practice in criminal defence and commercial litigation.

SUBSCRIBE

A weekly reading by post.

One short email each week — the most useful judgment of the week, distilled for advocates, CFOs, and founders. Free. Unsubscribe in one click.

By subscribing you agree to our Privacy & Disclaimers.