State firm can't use executive power in contracts, says SC
MP Power Management Co. terminated a solar PPA. The High Court intervened. The Supreme Court now clarifies when writ courts can review non-statutory contracts.
350
crores.
MP Power Management Co. terminated a solar PPA. The High Court intervened. The Supreme Court now clarifies when writ courts can review non-statutory contracts.
A state-owned power company tore up a Rs.350 crore solar deal. The company that lost it went to court. The Supreme Court just drew a line — and it changes everything.
In September 2015, M.P. Power Management Company Ltd. (MPPMCL) signed a Power Purchase Agreement (PPA) with M/s Sky Power Southeast Solar India Pvt. Ltd. The deal was straightforward: Sky Power would build three 50MW solar units, sell the electricity to MPPMCL at Rs.5.109 per unit, and complete pre-commissioning conditions within 210 days. If it missed that deadline, it could get a 9-month extension — but only by paying a penalty.
Sky Power missed the extended deadline by 56 days. MPPMCL terminated the agreement. Twice. Both times, the Madhya Pradesh High Court stepped in and set the termination aside. MPPMCL appealed to the Supreme Court, arguing that the High Court had no business interfering in a commercial contract. The Supreme Court agreed — but only partly. And in doing so, it clarified exactly when a state-owned company can use its government muscle in a business deal, and when it cannot.
The first termination letter, 11 August 2017
The first termination came on 11 August 2017. The letter — citing non-fulfilment of conditions subsequent — ended a deal that had already seen Sky Power invest heavily. Sky Power rushed to the Madhya Pradesh High Court, which set aside the termination on 20 June 2018, citing a similar case involving another company called Renew Clean Energy Pvt. Ltd. The court gave MPPMCL liberty to pass fresh orders.
MPPMCL issued a fresh termination on 7 July 2018. The High Court quashed that too, on 27 February 2020. MPPMCL filed a review petition on 28 December 2020; the High Court dismissed it. The case then reached the Supreme Court, where the final hearing took place in November 2022.
MPPMCL argued three things: the writ petition (a petition to the High Court asking it to review government action) was not maintainable because this was a private contract, Sky Power had clearly breached the conditions, and public interest favoured termination because power was now available cheaper in the market.
Sky Power countered that it had already invested Rs.350 crores, the project was nearly ready, and MPPMCL had acted arbitrarily — especially by treating Sky Power differently from Renew Clean Energy, which had received more favourable treatment in the High Court's earlier order. Sky Power also pointed out that MPPMCL had failed to issue a mandatory pre-termination notice under Article 9.1 of the PPA.
The ten issues the court framed
The Supreme Court framed ten distinct issues for determination. These ranged from the maintainability of the writ petition to the scope of judicial review under Article 14 for arbitrariness in contractual matters. The court examined whether the PPA was a statutory contract, whether disputed questions of fact barred writ jurisdiction, whether public interest considerations favoured termination, and whether MPPMCL had breached its duty of parity by treating Sky Power differently from Renew Clean Energy. The court also specifically considered the effect of MPPMCL's failure to issue the pre-termination notice under Article 9.1 of the PPA.
The core issue was deceptively simple: Can a High Court, under Article 226 of the Constitution (the power to issue writs to government bodies), review the termination of a non-statutory contract by a state-owned company?
MPPMCL argued that Article 226 does not allow courts to rewrite commercial contracts. If a party breaches a contract, the remedy is a civil suit for damages, not a writ petition. The High Court, MPPMCL said, had effectively become a contract manager, substituting its judgment for the company's commercial decision.
Sky Power argued that MPPMCL is "State" under Article 12 of the Constitution (the definition of government bodies bound by fundamental rights). As State, MPPMCL cannot act arbitrarily — even in a contract. If it does, Article 14 (the right to equality before the law) kicks in, and the High Court can intervene.
Why the Supreme Court said: both sides are right — but only partly
The bench, comprising Justice K.M. Joseph and Justice Hrishikesh Roy, held that there is no absolute bar on writ jurisdiction in non-statutory contracts. But it laid down a clear test: if the state-owned company's action is truly arbitrary — unprincipled, capricious, in bad faith, with an oblique motive, showing total non-application of mind, or wholly unreasonable in the Wednesbury sense — the High Court can step in.
But here is the critical distinction the court drew. Enforcing the consequences of a contractual breach is ordinarily not arbitrary. If a party misses a deadline and the contract says the agreement can be terminated, the state-owned company is simply doing what the contract allows. That is not arbitrariness. That is contract enforcement. The court cited the precedent of Kerala State Electricity Board v. Kurien E. Kalathil and ABL International Ltd. v. Export Credit Guarantee Corpn. of India Ltd. to support the proposition that writ jurisdiction is available in contractual matters where state action is challenged as arbitrary, but not for mere breach of contract.
The court also clarified a crucial point about the scope of executive power. A fully-owned government company may be "State" under Article 12 for the purpose of fundamental rights, but that does not mean it can exercise executive power under Article 162 (the extent of the State's executive power) or Article 298 (the power to carry on trade and make contracts). The broader Article 12 definition does not apply for Article 298 purposes. In plain terms: a state-owned company is bound by fundamental rights, but it cannot claim the privileges of the government when it enters a commercial contract.
When a contract becomes "statutory" — and why it matters
The court also addressed when a contract becomes a "statutory contract" — one that is subject to writ jurisdiction as a matter of course. A contract becomes statutory, the court held, when a statute mandates prescribed terms and conditions, making them compulsory components of the contract. If the terms are merely negotiated between parties, even if one party is a government company, the contract remains non-statutory. In such cases, the High Court can intervene only if the state-owned company's action is arbitrary in the constitutional sense — not merely a breach of contract.
This distinction matters because it determines the standard of review. For a statutory contract, any breach can be challenged by writ petition. For a non-statutory contract, the petitioner must show something more: arbitrariness, discrimination, or bad faith. The court cited the landmark case of Radhakrishna Agrawal v. State of Bihar to establish the framework for when writ jurisdiction is available in contractual matters.
The parity argument: why Renew Clean Energy mattered
One of Sky Power's strongest arguments was that MPPMCL had treated it differently from Renew Clean Energy, a similarly-situated party. The High Court had, in its first order, specifically cited the Renew Clean Energy case to set aside MPPMCL's first termination. Sky Power argued that MPPMCL's second termination was therefore discriminatory and violated Article 14.
The Supreme Court examined this argument closely. The court noted that if a state-owned company treats two similarly-situated parties differently without any principled basis, that action could be struck down as arbitrary. The court referred to the principle from Mohinder Singh Gill v. Chief Election Commissioner that every state action must be informed by reason. If MPPMCL had granted Renew Clean Energy additional time or leniency but denied the same to Sky Power, that could amount to arbitrariness.
THE PLAY: Before terminating a contract with a private party, a state-owned company must follow every contractual procedure to the letter — especially pre-termination notices — and must treat all similarly-situated parties identically, or the termination will be struck down as arbitrary under Article 14.
The judgment, delivered on 16 November 2022, ran through ten distinct issues before reaching its conclusion. The court ended where it began: with a Rs.350 crores deal, a missed deadline, and a question about how much power a state-owned company really has. The decision — a nuanced ruling that parsed the difference between contractual breach and constitutional arbitrariness — will echo through every future dispute between a government company and a private contractor.