COMMERCIAL DISPUTES  ·  SECTION 7(3) EXTENSION

The 3-factor test K-RERA uses to grant Section 7(3) extensions.

K-RERA granted a two-year extension to a project four years past deadline and only 32% complete, revealing the three factors that tip the scales under Section 7(3).

32

%.

Extended. After four years.
TL;DR

K-RERA granted a two-year extension to a project four years past deadline and only 32% complete, revealing the three factors that tip the scales under Section 7(3).

In this reading
1. One project. Four extensions. 32% complete. K-RERA says yes again. 2. The project that refused to finish 3. What the Authority actually looked at 4. The order: two more years, with strings attached 5. The doctrine that mattered: Section 7(3) as a safety valve 6. Why this matters for practitioners 7. The bottom line

One project. Four extensions. 32% complete. K-RERA says yes again.

When a real estate promoter walked into the Karnataka Real Estate Regulatory Authority (K-RERA) in February 2024, the numbers were brutal. The project had been registered since December 2018. The original deadline was August 2020. Four years later, only 32% of the work was done. The promoter wanted another two years.

K-RERA gave it to them.

This wasn't a case of a fly-by-night builder. The Authority had already granted three prior extensions — one automatic under COVID-19 rules, one statutory under Section 6 of the Real Estate (Regulation and Development) Act, 2016, and one discretionary under Section 7(3). Yet the project remained stubbornly incomplete. The question for every advocate, CFO, and founder reading this: when does the Authority say no? And what does a promoter have to show to keep the clock running?

The project that refused to finish

The promoter registered the project with K-RERA on 10 December 2018. The registration certificate set the validity from 1 June 2023 to 31 August 2020 — a curious timeline suggesting the project was already delayed at registration. Then COVID-19 hit. The Authority, like every RERA across India, granted a suo motu extension of nine months, pushing the deadline to 31 May 2021.

That wasn't enough. The promoter applied for and received a one-year statutory extension under Section 6 of the RERA Act, valid until 31 May 2022. Still incomplete. Then came the first extension under Section 7(3), taking the deadline to 4 November 2023.

By then, the project was 32% complete.

On 10 February 2024, the promoter filed another application under Section 7(3), seeking a further 12-month extension. The reasons: COVID-19 aftereffects, material shortages, labour disruptions, and economic slowdown. The same litany every builder in India has recited since 2020.

What the Authority actually looked at

K-RERA didn't just rubber-stamp the request. The order, dated 6 March 2024, shows the Authority examined three things: the project's physical progress (32%), the Annual Audit Report for 2022-23, and the promoter's representations about force majeure circumstances.

Critically, the Authority noted that no complaints against the project were pending. That's not a statutory requirement under Section 7(3), but it clearly mattered. A clean complaint record — even with glacial progress — made the extension easier to grant.

The Authority also considered the promoter's track record. The promoter had complied with all previous extension conditions, including filing returns and paying fees. No defaults. No litigation. No allottee grievances.

That combination — demonstrable force majeure, clean complaint record, and compliance history — was enough to tip the scales.

The order: two more years, with strings attached

K-RERA granted the extension until 6 March 2026 — roughly two years from the date of the order. That's longer than the 12 months the promoter asked for. The Authority clearly decided that a single, longer extension was better than serial short extensions that would require repeated applications.

But the extension came with conditions. The promoter must file monthly returns of project progress. The promoter must comply with all duties and obligations under the RERA Act. The Authority retained the power to revoke the extension if the promoter defaults.

This is the standard K-RERA approach: grant the extension, but keep the leash short. Monthly reporting means the Authority can spot trouble early. If the promoter misses two or three monthly filings, the extension can be pulled.

The doctrine that mattered: Section 7(3) as a safety valve

Section 7(3) of the RERA Act is the escape hatch for promoters who can't finish on time. It says: if the Authority is satisfied that the project is likely to be completed within a reasonable time, it may extend the registration period beyond the Section 6 extension.

The key word is "satisfied." The Authority doesn't have to be convinced the project will finish. It only has to be satisfied that completion is likely within a reasonable time. That's a lower threshold than certainty. And in this case, the Authority was satisfied.

What made it satisfied? Three factors:

The ratio is straightforward: Section 7(3) exists to prevent projects from dying mid-construction. If the promoter can show the delay wasn't its fault, and if the allottees aren't complaining, the Authority will likely grant the extension. The alternative — letting the registration lapse — would leave allottees stranded and the project in legal limbo.

Why this matters for practitioners

For advocates advising promoters, this order is a template. The application under Section 7(3) must do three things:

For CFOs and founders, the lesson is about cash flow and timelines. The RERA Act doesn't punish slow projects — it punishes abandoned projects. As long as you're making genuine progress, even at 32% after four years, the Authority will likely give you more time. But the cost is transparency: monthly reporting, annual audits, and constant communication with allottees.

For allottees, this order is a double-edged sword. The extension keeps the project alive, which is better than abandonment. But it also means waiting longer. The Authority's implicit message: a slow project with a responsible promoter is better than a dead project with a defaulting one.

THE PLAY: When applying for a Section 7(3) extension, lead with the force majeure evidence, show your clean compliance record, and offer monthly reporting as a condition — the Authority will almost certainly grant the extension if allottees aren't complaining.

The bottom line

K-RERA's order of 6 March 2024 confirms that Section 7(3) is not a trap for slow promoters — it's a lifeline. The Authority will grant extensions even at 32% completion, provided the promoter can show the delay was beyond its control and the allottees aren't harmed. The price of that lifeline is monthly transparency and ongoing compliance. For every promoter stuck with an incomplete project, the message is clear: keep filing, keep building, and keep talking to your allottees. The Authority will give you the time you need — but only if you earn it.

§    §    §

Reviewed by Sharad Bansal on 15 · 05 · 2026

Sharad Bansal — Sharad Bansal is an advocate of the Delhi High Court with twenty years of practice in criminal defence and commercial litigation.

SUBSCRIBE

A weekly reading by post.

One short email each week — the most useful judgment of the week, distilled for advocates, CFOs, and founders. Free. Unsubscribe in one click.

By subscribing you agree to our Privacy & Disclaimers.