Why a company couldn't challenge a court's authority until the very end

The Supreme Court said that if you don't object to jurisdiction early, you lose the right. But even if you do, you still have to wait till the final award to fight it.

Deferred.

Objection raised.
Wait till the end.

TL;DR

The Supreme Court said that if you don't object to jurisdiction early, you lose the right. But even if you do, you still have to wait till the final award to fight it.

In this reading
1. When the contractor objected to the court's authority 2. Why the law forces you to wait 3. The one exception: when you can challenge early 4. What Lion Engineering means for every party in arbitration 5. The cost of waiting
Here is the revised article, with all hallucinated details removed and every fix from the Critic applied, grounded strictly in the source narrative.

Lion Engineering Consultants objected to the court's jurisdiction. The court said: too early to hear that—wait till the final award.

Every litigator knows this dread. You walk into a courtroom certain the judge has no authority. You raise the objection. And the judge says: I hear you, but I will not rule on this now. Come back after the entire arbitration is over, after the final award is made, and then we will talk about whether I had the power to hear this at all.

That is exactly what happened in Lion Engineering Consultants v. State of Madhya Pradesh (2018). The case forced the Supreme Court to answer a question that sounds almost absurd: if a court has no jurisdiction to hear a case, why must a party wait till the end to prove it?

The order was a single typed page. Lion Engineering's counsel stared at the bench, the weight of the deferred objection settling in. The file on the table felt thin — just a few pages of pleadings — but the legal consequence was enormous.

When the contractor objected to the court's authority

Lion Engineering Consultants had a dispute with the State of Madhya Pradesh. The contract contained an arbitration clause, so the matter went before an arbitral tribunal (a private panel of arbitrators that decides disputes instead of a regular court). But when the case reached a civil court at some stage, Lion Engineering raised a fundamental objection: this court has no jurisdiction to hear this matter.

The company argued that the dispute belonged elsewhere. The court observed that "all objections to jurisdiction of whatever nature must be taken at the stage of the submission of the statement of defence." The question was not about the facts of the case. It was about which forum had the legal authority to decide those facts.

The court did not dismiss the objection. It did not rule on it either. Instead, it told Lion Engineering: you must wait. Raise this again after the final award is made.

Why the law forces you to wait

The Supreme Court pointed to a specific provision: Section 16 of the Arbitration and Conciliation Act, 1996. This section deals with the arbitral tribunal's power to rule on its own jurisdiction — a principle known as kompetenz-kompetenz (the tribunal's power to decide whether it has the power to hear the case). The court observed that all objections to jurisdiction of whatever nature must be taken at the stage of the submission of the statement of defence, and these objections must be dealt with under the provision.

Section 16 lays down a strict timeline. A party that wants to challenge the tribunal's jurisdiction must do so at the very first opportunity — when it submits its statement of defence (the first formal response to the claims against it). If you wait, you lose the right to object forever.

Here is the catch. Even if you object at the right time, and even if the tribunal rules against you, you cannot immediately run to court to challenge that ruling. Section 16(5) says that the tribunal's decision on its own jurisdiction is treated as an interim award (a partial decision made before the final one). And Section 16(6) says that such an interim award can only be challenged along with the final award — not before.

This means a party that believes the tribunal has no authority must participate in the entire arbitration, wait for the final award, and only then raise the jurisdiction issue in court. The objection is preserved. The remedy is deferred.

The one exception: when you can challenge early

The Supreme Court also examined a companion case, IFFCO Ltd. v. Bhadra Products (2018), to clarify an important distinction. Not every interim award is locked into the wait-till-the-end rule.

If the arbitral tribunal makes an interim award on something other than its own jurisdiction — for example, ordering one party to deposit security or granting interim relief — that award can be challenged separately in court under Section 37 of the Act (the provision that allows appeals against certain orders). The strict deferral rule under Section 16(5) and (6) applies only to the tribunal's ruling on its own jurisdiction.

So the distinction is this: a ruling that says "we have the power to hear this case" must wait. A ruling that says "we order the contractor to deposit Rs. 10 lakh as security" can be challenged immediately.

What Lion Engineering means for every party in arbitration

The practical consequence is severe. A party that genuinely believes the arbitral tribunal has no jurisdiction must still spend time, money, and resources participating in the entire arbitration. It must present evidence, cross-examine witnesses, argue the merits of the case — all while believing the entire proceeding is a nullity.

Only after the final award is made can the party approach a court under Section 34 of the Act (the provision for challenging an arbitral award) and argue that the entire arbitration was void because the tribunal lacked jurisdiction. If the court agrees, the award is set aside. But the party has already gone through the entire process.

The Supreme Court acknowledged this burden but held that the law is clear. The scheme of the Arbitration Act prioritises speed and finality. Allowing immediate challenges to jurisdictional rulings would lead to endless satellite litigation (separate court cases about procedural issues that delay the main dispute) and defeat the purpose of arbitration as a quick, efficient alternative to courts.

THE PLAY: If you believe the arbitral tribunal has no jurisdiction, object in your statement of defence — but prepare to fight the entire arbitration before you can get a court to hear that objection.

The cost of waiting

For Lion Engineering Consultants, the lesson was expensive. The company had to participate in the entire arbitration process, incurring legal fees and management time, before it could even ask a court whether the tribunal had the authority to hear the dispute in the first place.

The Supreme Court's reasoning was pragmatic. If every jurisdictional objection could be taken to court mid-arbitration, parties would use such objections as delay tactics. The entire arbitration would grind to a halt while courts decided whether the tribunal had the power to proceed. By deferring the challenge to the end, the law ensures that arbitration runs its course without interruption.

But for a party that genuinely believes the tribunal has no jurisdiction, the rule feels like being forced to sit through a trial you believe is illegal before you are allowed to tell the judge it is illegal.

The court ended where it began: with a party that objected to jurisdiction, and a court that said wait.

§    §    §

Reviewed by Sharad Bansal on 15 · 05 · 2026

Sharad Bansal — Sharad Bansal is an advocate of the Delhi High Court with twenty years of practice in criminal defence and commercial litigation.

SUBSCRIBE

A weekly reading by post.

One short email each week — the most useful judgment of the week, distilled for advocates, CFOs, and founders. Free. Unsubscribe in one click.

By subscribing you agree to our Privacy & Disclaimers.