You fired a contractor. You cited the wrong clause. The court said: too bad, termination still stands.
A tribunal upheld a termination under one clause after rejecting it under another. The High Court overturned it. The Supreme Court restored it, ruling that arbitrators can rely on any valid contractual ground.
30
years.
A tribunal upheld a termination under one clause after rejecting it under another. The High Court overturned it. The Supreme Court restored it, ruling that arbitrators can rely on any valid contractual ground.
IRCON terminated NBCC's contract citing Clause 60.1. The arbitrator said: not valid under that clause, but valid under Clause 17.4. The High Court said: you can't switch clauses. The Supreme Court said: actually, you can.
Two government companies. One construction contract. A termination notice that cited the wrong clause. And a legal battle that took nearly thirty years to settle one question: if you fire someone under the wrong rule, does the firing still count?
The answer, the Supreme Court ruled in March 2023, is yes — as long as the contract somewhere gives you the power to do what you did.
When the Vashi station project stalled
In April 1990, IRCON awarded a Rs. 3042.91 lakh contract to NBCC to build a Railway Station cum Commercial Complex at Vashi, Navi Mumbai. The deadline: 30 months. The site, which was meant to be a bustling transit hub, instead became a monument to stalled progress as the months slipped by.
NBCC did not finish on time. IRCON gave a special advance of Rs. 68 lakhs at 18% interest. Work slowed. Then it stopped. By early 1994, NBCC had practically abandoned the site — the equipment sat idle, the labour force had dispersed, and the silence on the construction plot was broken only by the wind.
On February 21, 1994, IRCON sent a termination letter. It cited Clause 60.1 — a provision allowing IRCON to end the deal if the contractor defaulted. The letter was crisp, formal, and pointed to a single clause. It did not mention the others.
The arbitrator found a different clause
NBCC challenged the termination by invoking arbitration (a private dispute resolution process where a neutral third party decides the case instead of going to court). The Arbitral Tribunal examined the evidence — the correspondence, the progress reports, the supplementary agreements — and reached a surprising conclusion: termination under Clause 60.1 was not justified. The facts did not fit that clause.
But the Tribunal did not stop there. It looked at the same contract and found another clause — Clause 17.4 — which made time the essence of the contract (meaning NBCC was bound to complete the work by the agreed deadline, and failure to do so was a breach serious enough to justify termination). Under Clause 17.4, the Tribunal held, the termination was valid. The arbitrator's table was stacked with files, and from that paper mountain, the Tribunal pulled out a different legal thread to justify the same result.
On that basis, the Tribunal rejected NBCC's Claims 33 and 34 — which sought refund of security deposits — and partly allowed IRCON's Counter Claim No. 3 for interest on the advances it had given.
The High Court said: you cannot switch clauses
NBCC went to the Delhi High Court under Section 34 of the Arbitration and Conciliation Act, 1996 (a provision that allows a party to challenge an arbitral award on limited grounds, such as the arbitrator exceeding its powers or the award being against public policy). The Single Judge set aside the parts of the award that had rejected NBCC's claims.
The reasoning: the arbitrator could not uphold the termination under Clause 17.4 after finding it invalid under Clause 60.1. IRCON had chosen its ground. It could not change it later. The Division Bench agreed when IRCON appealed under Section 37 (the provision for appeals against orders under Section 34).
The High Court's logic was intuitive — if you fire someone for one reason, and that reason fails, you cannot later say the firing was really for a different reason. But contract law, the Supreme Court would soon explain, does not work that way. The courtroom fell silent as the judges prepared to deliver a different view.
The Supreme Court restored the award
IRCON appealed to the Supreme Court under Article 136 of the Constitution (the provision that gives the Supreme Court discretion to hear appeals from any court or tribunal in the country). A bench of Justice M.R. Shah and Justice M.M. Sundresh heard the case.
The court held that the High Court had exceeded its jurisdiction under Section 34. The role of a court reviewing an arbitral award is limited. It cannot re-evaluate evidence and substitute its own view for the arbitrator's, unless the arbitrator's finding is perverse — so unreasonable that no reasonable person could have reached it.
The Supreme Court found nothing perverse about the Tribunal's reasoning. The Tribunal had examined the evidence, found that NBCC had abandoned the project, and concluded that the termination was valid under Clause 17.4 even if Clause 60.1 did not apply. The terminating party citing the wrong clause did not make the termination itself invalid, so long as the contract contained a clause that justified it.
The court cited its own precedent in Raveechee and Company v. Union of India (2018) 7 SCC 664, which had established a similar principle: the court reviewing an award cannot interfere merely because it disagrees with the arbitrator's interpretation of the contract.
The court observed, in a passage that cut through the procedural fog, that "the High Court has exceeded its jurisdiction under Section 34 of the Arbitration Act by substituting its own view for the well-reasoned findings of the Arbitral Tribunal." The weight of that sentence fell on the courtroom, a reminder that arbitration law does not permit a second guessing of the arbitrator's commercial wisdom.
Why the interest rate was cut
There was one modification. The Arbitral Tribunal had awarded IRCON interest at 18% on the advance given for hypothecation of equipment (a loan secured against machinery). The Supreme Court reduced this to 12% for the period during which the arbitration was pending — what lawyers call pendente lite interest (interest awarded from the start of arbitration until the award is passed).
The court relied on Section 31(7)(a) of the Arbitration Act, which gives arbitrators the power to award interest unless the contract specifically bars it. The contract between IRCON and NBCC did not mention interest on advances, but the court held that silence is not a bar. The bar must be clear and express. Since there was none, the arbitrator could award interest — but 18% was too high, and the court moderated it to 12%.
This part of the judgment was a quiet but significant correction. The smell of old paper from the contract files could not hide the fact that the document said nothing about interest. The Supreme Court filled that silence with a moderate rate, neither punishing the borrower nor rewarding the lender excessively.
What this means for every contract
For anyone who drafts, signs, or enforces commercial contracts, this judgment delivers a practical lesson. When you terminate a contract, you do not need to guess the exact clause that will hold up in arbitration. You need to show that the contract, read as a whole, gave you the right to terminate on the facts that existed.
For lawyers advising clients who have received a termination notice citing the wrong clause: do not assume the notice is invalid. The other side may still succeed if any clause in the contract supports the termination.
THE PLAY: When drafting a termination notice, cite every clause that could possibly apply — the arbitrator can later decide which one fits, but a notice that cites only one clause and gets it wrong may still be upheld if another clause justifies the same result.
The court ended where it began: with a contract, a termination, and a clause the terminating party never thought to mention.